
INTRODUCTION
Enhancing project performance during a "schedule crash" in a pharmaceutical environment is no straightforward task. Typically, it entails compressing the project's duration by adding more resources. This approach is high-risk as it usually leads to greater costs and diminished quality unless a solid infrastructure is put in place to mitigate the impact of changing the project plan. Project teams can create a viable infrastructure by using a combination of tried-and-tested project management practicesas well as Lean Six Sigma techniques.
In this article, we examine how to apply project management practices and Lean Six Sigma in a pharmaceutical automation environment to a schedule crash successfully. The article consists of two sections, starting with a case study that describes a successful schedule crash and followed by a brief discussion of baseline and complementary resources required for successful automation complianceand schedule crashing.
CASE STUDY
Crashing a schedule on budget and on quality
Part 1: Project definition and scope
Assess project needs and select the right tools
The subject of this case study is a Distributed Control System (DCS) validation project that was part of the automation of a new biotech pilot plant. In this project, schedule-crashing delivered a complex, compliant DCS to the plant below cost without compromising quality.
The scope of the project was DCS unit- and system-level testing, including:
The project assumptions and baseline were aligned with the client's corporate policies regarding
validation. The validation effort benefited from leveraging a controlled software library based on S88
standards, resulting in the elimination of a considerable amount of unnecessary testing. Once tested,
the library can be used multiple times and by multiple sites.
The software was developed using a modular approach, allowing the re-use of the same code multiple
times. This approach helped build a testing strategy that minimized redundancy and reduced risk. The
project spanned approximately 1.3 years and required a team of approximately 15 people with an
increase to about 30 during the "crashing" period.
Project Management Institute methodologies such as Earned Value reporting were used. The project
involved a high number of deliverables (approximately 7,000 documents) with complex workflows (for
remote and neighboring locations). It involved multiple team members and extensive documentation
review and approval. The project team exercised rigorous control over the process flow and the
progress of deliverables. Lean Six Sigma techniques for key metrics like cycle time measurement were
implemented to ensure proper focus on success factors. Specifically, the project management team
used the variance and Earned Value approach to verify the budget and schedule. Earned Value is a
forecasted variable used to predict whether the project will finish as per initial estimates.
The initial estimate of work was 11 months for 17 people. However, due to the fact that the facility
was a new pilot plant, the project team encountered a series of changes that expanded the scope of
the project and created rework. An updated schedule forecasted that the additional work would
require an additional 6 months at the existing planned pace. Since the imminence of the launch date
was the key business driver for the project, the revised duration was unacceptable. Consequently, the
project team needed to determine how to manage a "crash" in the schedule while respecting two
requirements: (1) maintain quality so as not to breach company policies and procedures as well as FDA
requirements; and (2) maintain cost.
As part of the schedule-crashing, the project team was doubled in less than 3 weeks.
Part 2: The challenge
Crash the schedule from 6 to 3 months and ensure project success
As mentioned earlier, the company was faced with two courses of action: (1) maintain current project delivery speed (hence delaying product launch) or (2) crash the schedule in an effort to meet the set launch date. Given that the launch involved multiple products with high value to the business, the decision was made to crash the project schedule by doubling the team within 2 to 3 weeks.
Crashing the schedule comes with a series of problems related both to cost and quality. The dangers of exponential cost overruns during a schedule crash are very real due to challenges tied managing a larger team and the potential for unforeseen inefficiencies. Quality may also be affected by the rapid ramp-up of the project team's size with new members whose training or knowledge set may not be sufficiently aligned with the project's specific dynamics.
As part of the transition planning, additional supervision requirements were identified to ensure smooth transitioning to the higher productivity model. The new work model involved striking the proper balance between overtime and bringing in new talent so as not to impact the team with attrition or burn out. Finally, ideas to maintain morale were discussed and planned. The level of outsourcing support was evaluated so as to help manage the rapid increase required to succeed.
During the project, the team continuously analyzed the process by using Lean Six Sigma tools. The team kept focusing on critical path activities to ensure that all efforts were kept on schedule (the crashed schedule); all the while, the team prepared for the next critical path activity to ensure success at each step. It devised a process flow diagram with key input and output variables and analyzed value- and non-value-added activities.
Figure 1: Improvement Area Process Map
This process map was used to discuss improvement areas for existing activities before crashing the
schedule. Duration and effort were reviewed and assessed for each activity. Opportunities for
becoming leaner were identified and later implemented.

A fishbone diagram was prepared to break out the root-cause categories of issues that had an impact on the process. Based on these results, the next drill-down exercise was to analyze why the scripts did not match the design specifications, repeating the combination of fishbone and Pareto tools to further isolate high-impact root causes. The following root causes were identified and analyzed using a Pareto chart (refer to Figure 2).
Not Match Design: Issues occurring when the software script (i.e. documented test case) did not match the design specification. This resulted in corrections to either test script documents or design specification.
Test Case Outline: Issues occurring when the test script cannot be executed as documented. Insufficient Information: Issues occurring when the design specification did not have sufficient information to write the test script.
Coverage: Issues occurring when the structure of the test script does not cover all potential testing scenarios from the design specification.
Not used template: Issues occurring due to formatting such as footer/header errors, page break, numbering.
Not used guideline: Issues occurring due to not respecting guideline information such as phases, interlock strategy.
File Name: Issues occurring specifically with respect to improper file naming of scripts, design specifications.
Design Issues: Issues occurring in design specification such as missing information, not matching functional requirements.
The team determined that one of the main causes was that the scripts were written according to an older version of the design and had not been updated. A tighter control prior to review was implemented, and the impact of these issues was significantly reduced.
Figure 2: Review of significant issues - Pareto
This process map was used to discuss improvement areas for existing activities before crashing the schedule. Duration and effort were reviewed and assessed for each activity. Opportunities for becoming leaner were identified and later implemented.

Issues with the least impact on the process were removed from the reviewing activities, further reducing the time needed to review the scripts. (Fortunately, negligible-impact issues were few in number, which made their removal that much faster.) Some of the key process flows were also further mapped according to Lean principles focused on cycle times, value-added and non-value-added activities.
Figure 3: Test Case Development and Execution
A snapshot of the activities required to approve test scripts for execution, highlighting the potential for lean improvements in both value- and non-value-added activities.

As expected, crashing the schedule had a huge impact on project management activities. Due to its high level of risk, crashing should be attempted only once the team is convinced that it is fast-tracking the project, that is has placed all activities in overlapping or parallel states to reduce duration as much as possible.
A countermeasures matrix was built to ensure that all potential risks of crashing were mitigated. Some of the key standard risks identified involved lack of control over resources, unclear project processes, diminished quality in deliverables, and unclear training guidelines for the ramped-up team.
Dealing with issues identified in the case study
The current Work Breakdown Structure (WBS) was reviewed to identify the impact of crashing on each activity. The detailed project plan was revised for each task in light of the accelerated project timeline. Root-cause analysis guided continuous improvement, and Lean techniques ensured improved workflow, removing delays and non-value-added steps.
Figure 4: Work Breakdown Structure (WBS)
The Work Breakdown Structure (WBS) provides the number of test cases and associated tasks for each
process cell - hence, the overall scope for the project. (Note: actual numbers of units and test cases
were factored.)

Daily reporting replaced weekly reporting for further control on Earned Value (EV) enabling better
monitoring and control of project progress. The key metrics were visually communicated to the entire
team, who became focused at surpassing the daily goals. EV provides a tangible measure of the actual
progress of work in relation to the planned value for the work. Too often, project teams measure their
progress against budgeted hours without any consideration for the deliverables. As a result, the project
team is not focused on completing the actual tasks in the required time. The team gets sidetracked by
preparing other deliverables that were not in the original scope, or by enhancing the level of quality
beyond the planned scope (scope creep).
The required granularity and frequency are important for EV management. A simple, visual graph of EV reported monthly (refer to figure 5) combined by detailed daily deliverable progress in the form of a table enabled the team to truly focus on completing critical daily tasks. The team understood each task that needed to be completed at the test script level and executed accordingly. A "Red Flag" alarm system was implemented to rapidly assess the situation and remove roadblocks to ensure success. The leadership objectives were focused on the roadblocks as planning, process flows, and deliverables were aligned and made clear to all the players (software programmers, testers, process engineers, document controllers etc.).
As part of the project crash, a revised detailed communication plan was presented to project stakeholders - the procurement, quality, engineering, automation, and validation teams - delivering real-time progress of all critical-path activities.
Figure 5: Earned Value Testing Effort
The Earned Value (EV) graph tracks project progress after crashing the schedule. The initial budget was maintained - a key attribute in defining project success. (Note: actual hours were factored.)

Lessons learned from the case study
Applying the principles of prototyping the project, the project team sat down and analyzed the data after 3-4 process cells delivered. A series of lessons were drawn and action plans were developed and implemented:
Conclusion
Crashing should be considered only after fast-tracking (overlapping all tasks as much as possible) has
been optimized. Crashing the project requires rigorous movement toward effective control of the
project through instructions, statistical monitoring of performance (control of the work processes),
and, when possible, mistake-proofing (see Figure 6, page 10).
It should be recognized that crashing has become a way of life for validation projects - and project
teams are embracing accelerated timelines as a normal part of their projects. Solid project
management understanding and know how, ensure flexibility to adjust the course of the project
efficiently and effectively. The team must also be ready to cope with a high degree of stress due to
heightened expectations. Hence, the leadership must motivate and communicate much more regularly.
Figure 6: Keeping control despite diminishing effort
Diminishing the effort for validation activities includes moving toward tools for more effective deployment of information and communication. The project was managed with the vision of moving toward mistake-proofing and statistical control when possible.

Due to the pharmaceutical industry's continuous focus on cost, businesses are innovatively trying to derive maximum value of each dollar invested in projects. Solid project management techniques combined with Lean Six Sigma provide the required framework to align metrics with execution for success - whether crashing or simply executing a project. This scientific methodology translates into less effort and greater control over the project during execution.
In this environment, project teams need to consider the time, dollar and quality continuums. Mitigating risks in each of these areas in a schedule crash situation is essential for meeting both project-team and stakeholder objectives.
DISCUSSION
Building an effective approach for schedule crashing
Using a baseline and selecting appropriate supporting standards
Facing multiple challenges is part of delivering a compliant automated system within a regulated environment. Management and the project team must address specific project needs to build the appropriate framework during initiation efforts. For automation projects in the pharmaceutical and biotech industries, there are four key areas that must be mastered to deliver a high-value, compliant, integrated project, namely:
Successful automation compliance: Legal regulations
Some of the key regulations pertinent to this type of automation project are:
National Electric Code (NEC)
Defining how the implementation of such a system meets the intended spirit of local, state and federal regulations is crucial. Laws are subject to interpretation, and understanding what is realistic and truly current Good Manufacturing Practice can make the difference between high cost and right cost.
Projects conducted in a regulatory environment must provide documented evidence that the product meets pre-determined specifications and quality. Extensive knowledge and experience of regulation requirements are needed to meet compliance requirements effectively. The "c" (current) in cGMPs becomes critical as interpretations of the legal requirements are in continual evolution, and team knowledge must be assessed frequently to ensure that it is current with regulations. Laws may offer much room for interpretation; therefore, interpretation is one of the greatest challenges for the industry. While it is cooperative to a degree, in general the industry is also quite conservative. Project team members may, in their quest for continuous improvement, create scope creep unnecessarily, resulting in overspending - a concern to financial stakeholders. Such outcomes, compounded over multiple projects, result in massive costs that, in the end, are transferred to patients.
Figure 7: Business Drivers for Success
In accordance with PMBOK, successful projects selectively mesh knowledge and practice components to ensure focused planning and execution. The above illustration has been customized from the PMBOK and adapted to the case study presented in this article.

The importance of company policies, guidelines and procedures
Without belaboring the point, another important prism for interpreting regulations is the company's own decision-making infrastructure, including its policies, guidelines and procedures:
Alignment with the above has been shown to yield greater customer satisfaction on a consistent basis.
Getting buy-in from senior management
No project team can get its work done without persuading senior management that its approach will yield benefits in terms of time and dollars - hence the crucial importance of getting senior management on-board. Project teams can build a strong case by focusing on the following considerations:
STANDARDS QUICK REFERENCE
Find out more about relevant industry standards and the organizations behind them: PMI (www.pmi.org) - ISA (www.isa.org) - ISPE (www.ispe.org) - IEEE-SA (www.standards.ieee.org)
ABOUT THE AUTHORS
Mark Cupryk is the VP and General Manager of Operations for Invensys Validation Technologies. He holds a Chemical Engineering degree from McGill University and a Master in Business Administration from Concordia University. He is also a certified Project Management Professional from the Pennsylvania Project Management Institute with a Master in Project Management. He has worked in automation and validation for over 15 years and is Lean Six Sigma Black Belt. Mark can be reached by phone at (617) 899-9264, by fax at (514) 485-6617 or by e-mail at mark.cupryk@ips.invensys.com.
Doina Morusca is a Senior Project Manager for Invensys Validation Technologies. She is specialized in both business and manufacturing systems with Lean Six Sigma. She holds a Master in Business Administration from Concordia University as well as a Master in Education. She is also a certified Project Management Professional from the Pennsylvania Project Management Institute. She can be reached by phone at (508) 878-6141 or by e-mail at doina.morusca@ips.invensys.com.
Dean Takahata is a Project Manager for Amgen. He holds an Engineering degree from Miami University and has worked in automation and project management for over 22 years. He has held various positions in project operations and software product development with ABB and Invensys. He can be reached by e-mail at deant@amgen.com.
ABOUT IVT
Invensys Validation Technologies (IVT) is recognized as the
industry leader in global regulatory compliance and business
systems solutions for the life science and process industries .
Services encompass the entire enterprise: equipment, process
control, cleaning control, automation, manufacturing execution
systems, and information technology.
IVT MISSION STATEMENT
"Together, we bring excellence"
We regard these values as essential to bring excellence;
Integrity - We are honest and true to our mission. It is the
foundation of our actions.
Team Work - We endeavor to bring out the best in each other;
to be more creative, productive and accountable.
Respect - We acknowledge individual's talents and differences.
We care about each other, our customers and partners. We communicate with openness and sincerity.
Improvement - We relentlessly seek ways to do better
internally and with our customers.
Leadership - We believe that leadership isn't about position;
it's about the attitude, skills and expertise we show every day.